
CASE STUDY · PIPELINE DELIVERY
Egwa II 8” × 4.3 km
Delivery Line Reconstruction
Fast-track project management from constructability and execution planning through pre-commissioning and operational readiness.
THE ASSIGNMENT
Execution speed
without losing control.
AVM, acting as Project Management Consultant to JCHL, managed the end-to-end delivery of the Egwa II reconstruction within the OML 42 environment.
Mobilisation commenced on 3 December 2024 and project completion was achieved on 8 January 2025. The delivery strategy combined constructability review, execution readiness, parallel work fronts and disciplined quality assurance.
EXECUTION STRATEGY
Designed for parallel progress.




QUALITY PERFORMANCE
Quality measured
at the weld.
Of 387 welded joints, 382 achieved first-pass acceptance. Five repairs were completed successfully, resulting in 100% final NDT acceptance.
PRE-COMMISSIONING
FROM CONSTRUCTION
TO READINESS.
The line progressed through flushing, pigging, gauge-plate inspection, hydrotesting, dewatering, drying and nitrogen purging as part of controlled pre-commissioning.
View OML 42 Programme →